Four trips out this week; Tuesday to check on a couple of things, Thursday for a meeting, Friday to take coffee to the boys and Sunday for Karen to see the week's progress.

The back "screen porch" deck is structurally complete. The second log columns supporting that roof are installed and the decking is 1/2 done. The insulator was still working Tuesday night but that is now complete. Framing is nearly complete in the basement, with just the bathroom dividing wall to finish. The electrician has started in the basement. The painters have started sealing the west walls and all the upper sections (soffit, facia, siding over the entry) are done. The soffit and trim around all the dormers is complete and the soffit for the front entrance is coming along nicely.

 